RENCANA BELANJA KEBUTUHAN
TAHAP I
No
|
Keterangan
|
Satuan
|
Volume
|
Total
|
Sub
Total
|
|
A.
|
Pembelian
Besi Bangunan
|
|||||
1
|
Besi
diameter 16 mm (ulir)
|
|||||
-
Sepatu 100/20
|
132,500
|
14
|
btg |
1,855,000
|
||
-
Kolom 30/30
|
132,500
|
14
|
btg |
1,855,000
|
||
-
Balok 30/60
|
132,500
|
40
|
btg |
5,300,000
|
||
-
Balok 20/30
|
132,500
|
4
|
btg |
530,000
|
||
-
Stekkan
|
132,500
|
3
|
btg |
397,500
|
||
Jumlah
|
75
|
btg |
9,937,500
|
|||
2
|
Besi
diameter 16 mm
|
|||||
-
Kuda balok 30/60 dan 20/30
|
125,000
|
16
|
btg
|
2,000,000
|
||
3
|
Besi
diameter 12 mm
|
|||||
-
Kolom 30/30
|
79,000
|
14
|
btg
|
1,106,000
|
||
-
Balok 30/60
|
79,000
|
30
|
btg
|
2,370,000
|
||
-
Balok 20/30
|
79,000
|
4
|
btg
|
316,000
|
||
-
Tangga
|
79,000
|
10
|
btg
|
790,000
|
||
Jumlah
|
58
|
btg
|
6,582,000
|
|||
4
|
Besi
diameter 10 mm
|
|||||
-
Slof 15/25
|
45,000
|
33
|
btg
|
1,485,000
|
||
-
Kolom 20/20
|
45,000
|
8
|
btg
|
360,000
|
||
-
Kolom 15/15
|
45,000
|
10
|
btg
|
450,000
|
||
-
Dak 1000/12
|
45,000
|
140
|
btg
|
6,300,000
|
||
Jumlah
|
191
|
8,595,000
|
||||
5
|
Besi
diameter 8 mm
|
|||||
-
Kolom 30/30
|
27,500
|
37
|
btg
|
1,017,500
|
||
-
Kolom 20/20
|
27,500
|
5
|
btg
|
137,500
|
||
-
Kolom 15/15
|
27,500
|
10
|
btg
|
275,000
|
||
-
Balok 30/60
|
27,500
|
64
|
btg
|
1,760,000
|
||
-
Balok 20/30
|
27,500
|
8
|
btg
|
220,000
|
||
-
Slof 15/25
|
27,500
|
32
|
btg
|
880,000
|
||
Jumlah
|
156
|
4,290,000
|
||||
Sub
Total A
|
29.404.500
|
|||||
No
|
Keterangan
|
Satuan
|
Volume
|
Total
|
Sub
Total
|
|
B.
|
Pembelian Material Bangunan | |||||
1
|
Semen Gresik 40 Kg/zak |
46,500
|
220
|
zak
|
10,230,000
|
|
2
|
Pasir hitam (cor) |
850,000
|
6
|
truk
|
5,100,000
|
|
3
|
Pasir pasang |
650,000
|
3
|
truk
|
1,950,000
|
|
4
|
Batu belah |
125,000
|
6
|
colt
|
750,000
|
|
5
|
Batu coral |
190,000
|
15
|
colt
|
2,850,000
|
|
6
|
Batu bata merah |
350,000
|
5
|
Rb
|
1,875,000
|
|
6
|
Multiplek (tebal 8 mm) |
100,000
|
66
|
lbr
|
6,600,000
|
|
7
|
Bendrat |
6,500
|
20
|
Kg
|
130,000
|
|
8
|
Kayu 6 x 12 x 400 Cm |
60,000
|
25
|
btg
|
1,500,000
|
|
9
|
Kayu 5 x 7 x 400 Cm |
30,000
|
91
|
btg
|
2,730,000
|
|
10
|
Paku 1,5 inch |
14,000
|
5
|
Kg
|
70,000
|
|
11
|
Paku 2,5 inch |
14,000
|
5
|
Kg
|
70,000
|
|
12
|
Sewa molen |
250,000
|
1
|
Hr
|
250,000
|
|
13
|
Ember cor |
8,000
|
10
|
Bh
|
80,000
|
|
14
|
Bambu |
15,000
|
125
|
btg
|
1,875,000
|
|
36.060,000
|
||||||
C.
|
Instalasi Listrik dan Air | |||||
1
|
Instalasi listrik dan air |
5,000,000
|
1
|
pack
|
5,000,000
|
|
5,000,000
|
||||||
D.
|
Upah Kerja | |||||
1
|
Tukang 50 hari x 3 orang |
60,000
|
150
|
HOK
|
9,000,000
|
|
2
|
Pembantu 50 hari x 3 orang |
45,000
|
150
|
HOK
|
6,750,000
|
|
15,750,000
|
||||||