Senin, 12 Desember 2011

Rencana Belanja Kebutuhan Tahap I


RENCANA BELANJA KEBUTUHAN
TAHAP I


No
Keterangan
Satuan
Volume
Total
Sub Total
A.
Pembelian Besi Bangunan





1
Besi diameter 16 mm (ulir)




- Sepatu 100/20
132,500
14
btg
1,855,000


- Kolom 30/30
132,500
14
btg
1,855,000


- Balok 30/60
132,500
40
btg
5,300,000


- Balok 20/30
132,500
4
btg
530,000


- Stekkan
132,500
3
btg
397,500


Jumlah

75
btg

9,937,500
2
Besi diameter 16 mm






- Kuda balok 30/60 dan 20/30
125,000
16
btg
2,000,000

3
Besi diameter 12 mm






- Kolom 30/30
79,000
14
btg
1,106,000


- Balok 30/60
79,000
30
btg
2,370,000


- Balok 20/30
79,000
4
btg
316,000


- Tangga
79,000
10
btg
790,000


Jumlah

58
btg

6,582,000
4
Besi diameter 10 mm






- Slof 15/25
45,000
33
btg
1,485,000


- Kolom 20/20
45,000
8
btg
360,000


- Kolom 15/15
45,000
10
btg
450,000


- Dak 1000/12
45,000
140
btg
6,300,000


Jumlah

191


8,595,000
5
Besi diameter 8 mm






- Kolom 30/30
27,500
37
btg
1,017,500


- Kolom 20/20
27,500
5
btg
137,500


- Kolom 15/15
27,500
10
btg
275,000


- Balok 30/60
27,500
64
btg
1,760,000


- Balok 20/30
27,500
8
btg
220,000


- Slof 15/25
27,500
32
btg
880,000


Jumlah

156


4,290,000

Sub Total A




29.404.500




No
Keterangan
Satuan
Volume
Total
Sub Total
B.
Pembelian Material Bangunan





1
Semen Gresik 40 Kg/zak
46,500
220
zak
10,230,000

2
Pasir hitam (cor)
850,000
6
truk
5,100,000

3
Pasir pasang
650,000
3
truk
1,950,000

4
Batu belah
125,000
6
colt
750,000

5
Batu coral
190,000
15
colt
2,850,000

6
Batu bata merah
350,000
5
Rb
1,875,000

6
Multiplek (tebal 8 mm)
100,000
66
lbr
6,600,000

7
Bendrat
6,500
20
Kg
130,000

8
Kayu 6 x 12 x 400 Cm
60,000
25
btg
1,500,000

9
Kayu 5 x 7 x 400 Cm
30,000
91
btg
2,730,000

10
Paku 1,5 inch
14,000
5
Kg
70,000

11
Paku 2,5 inch
14,000
5
Kg
70,000

12
Sewa molen
250,000
1
Hr
250,000

13
Ember cor
8,000
10
Bh
80,000

14
Bambu
15,000
125
btg
1,875,000







36.060,000
C.
Instalasi Listrik dan Air





1
Instalasi listrik dan air
5,000,000
1
pack
5,000,000







5,000,000
D.
Upah Kerja





1
Tukang 50 hari x 3 orang
60,000
150
HOK
9,000,000

2
Pembantu 50 hari x 3 orang
45,000
150
HOK
6,750,000







15,750,000